Aikin tozarta tsibirin Crab yana zuwa da kyau

The Gold Coast Waterways Authority's (GCWA) na farko aikin hakowa na 2023 ya fara kwanan nan a ƙarshen ƙarshen tashar West Crab Island.

Aikin yana mai da hankali ne kan daidaita gadaje da ɗigon yashi, tare da cire yashi kusan mita 23,000 na yashi kuma a sake amfani da shi cikin fa'ida don ciyar da buɗaɗɗen bakin teku a Narrowneck.

Aikin ya karfafa kan gagarumin aikin noman ruwa na GCWA a shekarar 2020, wanda ya ga yashi cubic mita 30,000 da aka cire daga kudancin tashar, yana tallafawa hanyar shiga marinas, wuraren masana'antu, cibiyoyin sabis da magudanar ruwa zuwa yammacin tashar.

GCWA-ya kaddamar da-aikin-farko-farko-na-2023

A halin yanzu, tashar tashar West Crab Island (arewa) aikin ɓarkewar 25% cikakke ne tare da yashi cubic 7,550 da aka cire daga gaɓar teku zuwa yanzu.

Fiye da tafiye-tafiye guda 20 an yi daga Paradise Point zuwa wurin ajiya na Narrowneck tun lokacin da aka fara aikin a farkon Fabrairu, in ji GCWA a cikin sabuntawa.

Ana shirin kammala aikin tashar tashar West Crab Island ta arewa zuwa Afrilu 2023.


Lokacin aikawa: Maris-07-2023