The Gold Coast Waterways Authority's (GCWA) na farko aikin hakowa na 2023 ya fara kwanan nan a ƙarshen ƙarshen tashar West Crab Island.
Aikin yana mai da hankali ne kan daidaita gadaje da ɗigon yashi, tare da cire yashi kusan mita 23,000 na yashi kuma a sake amfani da shi cikin fa'ida don ciyar da buɗaɗɗen bakin teku a Narrowneck.
Aikin ya karfafa kan gagarumin aikin noman ruwa na GCWA a shekarar 2020, wanda ya ga yashi cubic mita 30,000 da aka cire daga kudancin tashar, yana tallafawa hanyar shiga marinas, wuraren masana'antu, cibiyoyin sabis da magudanar ruwa zuwa yammacin tashar.
A halin yanzu, tashar tashar West Crab Island (arewa) aikin ɓarkewar 25% cikakke ne tare da yashi cubic 7,550 da aka cire daga gaɓar teku zuwa yanzu.
Fiye da tafiye-tafiye guda 20 an yi daga Paradise Point zuwa wurin ajiya na Narrowneck tun lokacin da aka fara aikin a farkon Fabrairu, in ji GCWA a cikin sabuntawa.
Ana shirin kammala aikin tashar tashar West Crab Island ta arewa zuwa Afrilu 2023.